CLIENT | South Kent School Kent, CT |
---|---|
PROJECT HIGHLIGHTS | CTDEEP 27,500 GPD On-Site Disposal and Collection System Upgrade and Expansion for growth to 220 students; completed in two phases inclusive of a commercial grade pump station, a digitally controlled distribution system for various cells, actuarial controlled valves, computerized reporting of flows to desktop and emergency power |
CONSTRUCTION COST | $590,000 |
College Preparatory School
This school in South Kent CT was expanding and needed a larger on site water and wastewater system. Mark E. Lancor P.E., principal engineer at DyMar designed a conventional system that met the State Department of Energy and Environmental Protection discharge limits. Leggett, Brashears and Graham, a hydro geological consultant in Shelton CT used the MOD-Flow three-dimensional finite-difference groundwater model to calibrate hydrologic flow.
The Project went out to bid based on components. Mark Green, manager of HLC Excavations and Tank Removal in Woodbury CT won the contract to install the dose tank and drain field. Unsuitable soils, logistics, high groundwater and bad weather stretched a two month installation from September through early March.
Site Conditions
Soils are sand and gravel with 6-8 inch cobble and permeability rates of 2.5 to 28 feet per day. The water table is 8- 9.5 feet below grade. The drain field is sited by a pond, wetlands and a road
System Components
Mark Lancor designed the system to handle 27,476 gdp. Major components are:
- 7,500-gallon dose tank with three 3-hp Barnes effluent pumps (Crane Pumps and systems)
- 11x 6 foot wide concrete vault (Connecticut Precast Corp.) with 3 inch electromagnetic flow meter (Milwaukee Valve)
- 7 square foot concrete splitter vault with 3 inch ball valves and check valves
- 1,164 Contactor 100 chambers (CULTEC) in a 59,400 square foot drain field.
- Custom control panel from SPI – Septic Products.
“We often had to over-excavate to extract the cobble, then go back two feet and re-establish the subgrade with finer material. We did that for 4,329 feet, which is a lot of digging for four people, but I had no room for a second crew.” Mark Green
System Operation
Wastewater flows from numerous buildings and pretreatment septic tanks through 6X3 inch force mains to the dose tank. Alternating on demand pumps run 15 minutes, sending 1,528 gallons at 46 feet total dynamic head to the metering vault. (during high flows, two pumps run simultaneously) Two 3 inch force mains carry the metered flow to the splitter vault, which alternatively does each zone’s distribution box with5,000 gallons per cycle.
In the vault, flow A splits four ways: A 2 inch force main feeds paired drain fields 1-2, a 1.5 inch pipe feeds drain fields 3-4 and 5, and a 2 inch line feeds drain fields 6-7. Flow B splits three ways: A 1.5 inch force main feeds drain field 8, a 2 inch pipe feeds drain field 9 and a 2.5 inch line feeds drain field 10.
The drain field has eight zones of seven laterals, either 68.75, 75, or 87 feet long. Approximately 240 feet of additional chambers drain stormwater from the soccer field.
Water and Wastewater System Installation
Green, two machine operators, and a laborer stripped and stockpiled 4,100 cubic yards of topsoil from the drain field area, then brought in a screener and front-end loader to screen the material. “We had topsoil pushed into little mountains all over the east side of the site”, says Green. “Then we had to find enough room to stockpile the screenings and tailings.”
Using a Komatsu PC 128 excavator to dig 72 inch wide trenches 2 to 4 feet deep, the crew quickly encountered an unending supply of cobble that they dug out, stockpiled and screened to an acceptable backfill material. The fact that the trenches required no bedding presented another challenge.
“It was tough to keep the trenches tight, find enough fine gravel for a level base and maintain elevations,” says Green, who constantly checked grades with a laser and LL500 laser level (Spectra Precision).
Trenching advanced 300 feet per day. After the team installed two rows of 96x35x12.5 chambers, they covered them with No. 410 nonwoven filter fabric (CULTEC) and backfilled to the crowns with 1.25 inch stone. Then they returned with the screener to sift the excavated material, covered the stone with 6 inches of it, and finished with 6 inches or more of topsoil to grade. Tailings were deposited along stream bank or other areas needing fill.
To avoid trapping themselves into a corner, the crew installed one zone at a time working west to east, then used the completed zone as a platform to install its neighbor. The Komatsu excavator, rated up to 30,000 pounds, safely tracked over the H10 rated chambers. “it was like working on a jigsaw puzzle,” says Green
The excavations for the 14x20x10 pump tank was across a road from four residences, 5 feet from a heavily flowing stream on the other side and 10 feet below the water table. The crew quickly encountered severe water conditions. Green called groundwater specialists Dauti Masonry in Prospect CT to help install a wet well and two 1/3 hp submersible pumps running continually to dewater the40x14 feet deep excavation.
“We benched and excavated more than 1,000 cubic yards of material by running an Hitachi EX200 excavator and dump truck 10 hours per day,” says Green. “As fast as the material came out, we stabilized the banks with stone.” The excavation required 1.25 inch stone 6 to 8 inches deep.
A trucking company brought the tank in four sections, and A-Quick Pick Crane and Rigging set them. The bottom section alone weighed 10 tons. Once the joints were solvent-welded together, Green’s crew wrapped the sides of the tank in urethane sheets and sealed them with propane torches. They sealed the inlets and outlets with waterproofing grout (Five Star Products), then tested the tank for water tightness.
Green also installed the splitter vault 700 feet from the metering vault, and used 50 psi hydraulic pressure to test the force mains going to the drain field. The normal pressure is 37 psi.
Heavy rains stopped work in October, the soil froze two feet deep in December, a blizzard buried the site in January and the project finally resumed in mid-February. The system went operational in early March.
Water and Wastewater System Maintenance
Waste & Water Equipment of Cromwell CT installed the control panel and maintains the water and wastewater system.